Rebuild Key Project Update

august 2018 rebuild update timelines

Over the next few months,  we expect to make significant progress on several of our infrastructure rebuild projects.

Below is a short summary, a longer rebuild update will be available by the end of September. 

 

Download a PDF of where the key projects are currently at (August 2018)

 

Key projects:

Five Bridges

Current state: out for tender

Next step: contract to be evaluated and negotiated

Key notes: Hawthorne and Gillings Land first priority

Lyell Creek Sewer

Current state: concept design

Next step: detailed design to be priced

Key notes: construction contract could start early 2019

Aeration Lagoon

Current state: concept design

Next step: detailed design to be priced

Key notes: construction contract should start in November

Totara Lane Pump Station

Current state: detailed design

Next step: detailed design to be priced by contractors

Key notes: construction could start in October/November

Ford reservoir

Current state: detailed design nearly completed

Next step: detailed design priced by contractors

Key notes: construction could start in November

Clarence Valley Access

Current state:Indicative Business case being carried out

Next step: Indicative Business case completed end of October

 

 

Useful links:


17 August 2018